Normal Duration

The normal duration of a project is the time between the early start and early finish dates, assuming that the late start date is after the early start date.

A task bar showing normal task duration and slack time

Notes

  • The colors shown reflect the default style. The actual colors might be different.
  • In some charts, the slack time might not be indicated. In that case, the time between the early start date and the late start date is shown as the normal duration.